A $1 billion Google data center was negotiated for two years before the public knew a thing.

Now they want our water, our power, and our land. We're not asking permission to be heard. We're demanding it: a one-year moratorium, full transparency, and a real voice before a single permit is signed.

Fast Facts

Project Timeline

2023
Data Centers Act of 2023

Arkansas law, every legislator present voted for it - Dems & GOP

2023
A secret courtship, and a 12-hour land vote

The Chamber courts Google (under the name Willowbend Capital, LLC) and other data centers under NDAs. Land near the Port is teed up for sale with as little as twelve hours' public notice, leaving no real time for comment. MOU is signed 65% property tax abatement for 30 years (highest state allows). Also allows for future data centers with this company.

2023-2024
Land annexation and rezoning for Google by LR planning commission - June 12

https://www.arkansasonline.com/news/2025/jun/13/little-rock-port-annexation-for-amazon-expansion/

2023-2024
A newspaper, not an official, names Google

The Arkansas Democrat-Gazette reports Google is behind the $1 billion Port of Little Rock project. Residents learn the scale of what's been planned for them.

Army Corps filing exposes the true footprint
A federal document reveals 1.43 million square feet across five industrial buildings plus a dedicated electrical substation, dwarfing the figure shared with the public. Google withdraws this application in June.

Take Action Now

Make your voice heard at City Board of Directors Meetings.

Attend the next City Board of Directors Meeting Find your Board Member

Upcoming Events

City Board of Directors Meeting

September 8 - 6:00pm

Town Hall Meeting

September 22- 6:00pm